Waun Maenllwyd: what is actually proposed

Six turbines up to 200 m on the Cambrian Mountains near Llanddewi Brefi. Every figure below is taken from the applicant's own documents, with the page to check it.

–days left to comment (PEDW DNS CAS-02650-B0P0M9)

Fact sheet: the applicant's own figures

From the Environmental Statement and supporting documents. Page numbers are PDF pages.

ItemValueSource

Noise at homes: the applicant's numbers, rebuilt independently

40 dB+38–40 dB35–38 dB30–35 dBAddressed buildings at 30 dB+ (100 m squares)
Day-time limit used by applicantPredicted, standard operationPredicted, with three turbines slowed

What this shows

    Check our model against the applicant's table (LA90 dB)

    Where the turbines could be seen

    Map of where blade tips would be theoretically visible within 20 km, shaded by number of turbines
    Bare-ground visibility of blade tips, rings at 5, 10, 15 and 20 km. Darker = more turbines in view.
      A 200 m Waun Maenllwyd turbine drawn to scale beside a house, oak tree, pylon, Elizabeth Tower, St Paul's Cathedral and Blackpool Tower

      The applicant's own viewpoints, rendered independently

        Shadow flicker: checked, and mostly not a problem here

        The group re-ran the applicant's shadow flicker test with better terrain. The honest result is below, including where it supports the applicant.

          Energy and carbon: the applicant's method, realistic inputs

            Explore it yourself

            The same turbines, on real LiDAR terrain. Open the 3D model to see the turbines and noise across the landscape, or pick your own home and see the view before and after.

            See it in 3D with noise

            Opens on Waun Maenllwyd with all six turbines placed, the terrain loaded and the noise map calculated. Check the predicted level at any property.

            Open the 3D model

            The view from your home

            Search your postcode, choose where you stand and which way you look. Switch between before and after, and share a link to your exact view.

            Open the view finder

            Turbine positions and heights from the application (ES Ch 3, Table 3.1). Views are worst case: bare ground, no trees or buildings screening them.

            Questions the fact sheet raises

            Starting points for scrutiny, not conclusions. Each will be tested with the tools below.

            How the tool is built

            Six layers, built one at a time on this scheme, then reused for others.